StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

COURT DISMISSES CONDEMNATION PETITION - Finds Grain Belt Express did not negotiate in good faith

1/13/2023

1 Comment

 
Picture
On December 31, 2022, the Circuit Court of Monroe County found that Invenergy subsidiary Grain Belt Express did not negotiate in good faith with Monroe County, Missouri landowners and did not give them all of the notices required by Missouri law.

The Court found that Grain Belt's notices to the landowners did not disclose the exact location of the easement area; did not give a description of all of Grain Belt's proposed uses of the land; and that Grain Belt's required appraisal of the land omitted a significant portion of the easement rights sought by Grain Belt and also omitted a portion of the owner's land from consideration.
It is therefore the ORDER of this Court that Plaintiffs Petition in Eminent Domain is DISMISSED without prejudice. The Court, pursuant to the requirements in Section 523.256 RSMo, orders Plaintiff to reimburse the owners for their reasonable attorney's fees
and costs incurred with respect to this condemnation proceeding. Defendants may file appropriate motions requesting the same.
You can read the Court's Findings of Fact and Conclusions of Law here:
monroe_co_gbe_findings.pdf
File Size: 3533 kb
File Type: pdf
Download File

The Court found Grain Belt's notices to the landowners did not meet the requirements of Missouri law because they never mentioned "ingress and egress" rights over the owner's land outside the easement on which GBE wanted to construct roads, crossings and culverts, and install gates.  The ingress/egress rights were mentioned for the first time in the condemnation petition, therefore the landowners were not given adequate notice. 

Another problem with Grain Belt's notices is that they never gave the landowners the exact size or location of the easement.  GBE's description of the easements and acreage changed from time to time, as noted on the table the judge included in her findings.  Missouri law requires that the landowner be notified that he may obtain his own appraisal, and the judge found that because GBE never disclosed the exact size and location of the easement, it prevented the landowner from obtaining an appraisal because an appraiser cannot appraise property that is not defined.

The findings revealed that GBE's appraiser did not consider the portion of the owner's property across the highway in his appraisal, and did not include the ingress/easements rights in his written report.  The Court said:
On direct, the appraiser for Plaintiff testified that he took into account the ingress/egress rights, in spite of omitting them from his report. The Court recognizes that it has the authority to consider the credibility of an appraiser's testimony at a condemnation hearing. Planned Indus. Expansion Auth. of Kansas City v. Ivanhoe Neighborhood Council, 316 S.W.3d 418,425 (Mo.App. W.D. 2010), as modified (June 1, 2010). This Court "is not required to take the appraisers' testimony at face value." Id. at 428. With that consideration, the Court gives more weight to the fact that the written appraisal report omits a significant portion of the easement rights sought in the Petition and thus did not include
compensation for the omitted rights. As to the appraiser's testimony to the contrary, the Court attributes bias to the witness who has already obtained significant compensation for his services and stands to gain significantly more in the course of this Project.
If GBE is threatening to condemn your land, you should definitely hold on to this case to give to your own lawyer when the time comes.

I wonder how many other times GBE's crack team of attorneys and appraisers have not negotiated with landowners in good faith?  And why did the Missouri PSC grant eminent domain authority to a company without the requisite skills and experience to negotiate in good faith with landowners?
1 Comment

Grain Belt Express Wants a Taxpayer Handout

12/23/2022

2 Comments

 
Picture
Or maybe we should call this "Solyndra 2.0"?

A week ago, the U.S. Department of Energy published a notice in the Federal Register entitled, "Notice of Intent To Prepare an Environmental Impact Statement for the Grain Belt Express Transmission Line Project."

You can read the whole thing here, or see the less technical version on GBE's brand new website.

To summarize, GBE has applied for a federal loan guarantee to build "Phase 1" of its project.  This taxpayer-funded gravy train is administered by the DOE, and because it now involves the federal government in the GBE project, the government is required to conduct an Environmental Impact Study under federal law (National Environmental Policy Act, or NEPA).
Title XVII of the Energy Policy Act of 2005 (EPAct) established a federal loan guarantee program for certain projects that employ innovative technologies. EPAct authorizes the Secretary of Energy to make loan guarantees available for those projects.  Grain Belt Express, LLC (Applicant), has applied for a loan guarantee pursuant to the DOE Renewable Energy Project and Efficient Energy Projects Solicitation (Solicitation Number: DE-SOL-0007154) under Title XVII, Innovative Energy Loan Guarantee Program, authorized by the EPAct. The primary goal of the program is to finance projects and facilities in the United States that employ innovative and renewable or efficient energy technologies that avoid, reduce, or sequester anthropogenic emission of greenhouse gases (GHGs).
When did this happen, you may wonder?  Nobody knows.  DOE conducts its guaranteed loans of taxpayer dollars in complete secrecy.  You don't get to comment about that, but they do have to let you comment about the environmental effects of GBE because of NEPA.

But I'm much more concerned about the federal government "loaning" GBE billions of dollars to construct a project that doesn't have an adequate revenue stream to pay back the loan.  What kind of a government geek thought this would be a good idea?  What kind of due diligence have they performed?  Doesn't sound like it was much... and that's how Solyndra happened.  The government loaned taxpayer funds to a company it didn't really investigate and the company went belly-up before repaying the loan.  That means that the taxpayers were never repaid.  But Solyndra lived high on the hog on taxpayer funds before the bill came due.  All that money... gone with the wind simply because some government functionary was lazy or under political pressure to approve a loan that any rational banker would run away from.  And here's another worry... what if GBE also has applied for a taxpayer-funded "capacity contract" from the DOE?  In that instance, DOE would pay GBE for its project (although it wouldn't actually USE it) for a period of 40 years.  So, what if GBE repays the taxpayer loan with taxpayer capacity contract funds?  Does that mean that we would repay the loan we made to GBE?  This is the epitome of bloated government waste.  Just throw around a bunch of taxpayer funds and "clean energy" will magically happen!  Or  maybe a bunch of well-connected rich guys will simply fill their pockets and zoom off into the sunset.  That's probably more like it!

Meanwhile, the DOE must evaluate the environmental effects of GBE, and it wants to do it in record time.

The first step of this process is what they call "scoping."  The scoping process collects public comment and uses that to set the parameters of what will be studied.  They want to hear your thoughts on
Potential impacts on resources include, but are not limited to, impacts (whether beneficial or adverse; short term or long term) on air quality and GHG emissions; soils and paleontological resources; water resources, including surface and groundwater and floodplains; vegetation, wildlife, and special-status species; land use and recreation; socioeconomics and environmental justice; public health and safety; cultural resources and Native American traditional values; transportation; visual resources; and noise.
And DOE plans to gather your comments before the end of February, 2023.  You may comment:
LPO will hold six public scoping meetings for the project, four in-person and two virtual meetings, at the following dates and times (Central Time). Registration for the virtual public meetings may be completed at the following web links:


• Wednesday, January 25, 2023, 11:30 a.m.-1 p.m., virtual meeting on Zoom ( https://us06web.zoom.us/​webinar/​register/​WN_​NOQzgumNTpOAIL5UoLVIeA)
• Thursday, January 26, 2023, 5 p.m.- 6:30 p.m., virtual meeting on Zoom ( https://us06web.zoom.us/​webinar/​register/​WN_​D619NGe1TGqMH0fcHx5SSA)
  • Tuesday, January 31, 2023, 11 a.m.-1 p.m. and 4 p.m.-6 p.m., Dodge House Hotel and Convention Center, 2408 W Wyatt Earp Blvd., Dodge City, KS 67801
• Tuesday, January 31, 2023, 11 a.m.-1 p.m. and 4 p.m.-6 p.m., Municipal Auditorium, 201 W Rollins St., Moberly, MO 65270
  • Thursday, February 2, 2023, 11 a.m.-1 p.m. and 4 p.m.-6 p.m. Corinthians Hill Event Center, 464 NE 20 Ave., Great Bend, KS 67530
  • Thursday, February 2, 2023, 11 a.m.-1 p.m. and 4 p.m.-6 p.m., Fairview Golf Course, 3302 Pacific St., St. Joseph, MO 64507


All meetings are open to the public and free to attend.
DOE will gather this information and then present a number of "alternatives" that they will study.  There are currently only two alternatives -- to build the project as proposed, or to not build the project at all.  There is no middle ground, such as building the project buried on existing highway or rail rights of way so that it doesn't affect the environment at all, certainly to a much lesser degree.  However, the DOE is also asking for your thoughts on possible alternatives that they have not yet thought of (such as burial on existing ROWs).

Once DOE has its alternatives and study parameters, it will study how each alternative effects the environment, and publish a draft study (estimated to be September 2023).  The public will once again be asked to comment on the draft study to tell DOE what they got wrong, or what they excluded.  DOE will take those comments and revise its study to produce a final Environmental Impact Study (estimated to be July 2024).  Once DOE has the final study, it will make a decision on which alternative to pursue no sooner than 30 days after publication.

Seems kind of quick, doesn't it?  Especially the scoping period, which begins just one short month after announcing the process on December 16.  As if you don't already have enough to do with the holidays and participating in your own state's public utility commission  hearings on GBE.  Now you just got a whole bunch more work dumped on you.  If you can't keep up, then DOE doesn't have to consider your comments and will just give GBE what it wants -- billions of your tax dollars.

I'm not going to go into a long narrative of what you should do here.  Please check in with your group leadership to see what the plan is. 

Ho Ho Ho from greedy GBE, who doesn't seem to have enough customers to pay for its project and now wants YOU to pay for it.  Santa is putting coal in GBE's stocking this year.
2 Comments

Urban Special Interest Groups Pretend to Represent Rural Landowners

12/23/2022

2 Comments

 
It takes real audacity to claim to speak for people you've never met, never talked with, and know absolutely nothing about.  But that never stopped a well-funded, urban, special interest group before.  They think they know everything about everything because they wish it to be so.

It's almost comical -- a bunch of urban special interest groups got together and wrote a letter to their oracle, Joe Biden, and told him what rural landowners affected by new transmission want.
Picture
Now more than ever, we need strong environmental review and public engagement processes to avoid harming communities while effectively speeding up development of much-needed infrastructure to enable a rapid clean energy transition.
"Public engagement".  What does that mean?  Simply giving landowners "notice" and allowing them to blow off steam with "input" doesn't solve the problem.
A recent study from MIT concludes that a significant hurdle in developing clean energy infrastructure projects is local opposition --and early community engagement can avoid delays or cancellations. To address this major slow down and to ensure that our new transmission is developed in an equitable manner, we must work with the very communities that our infrastructure is supposed to serve and not against them.
But yet these special interest groups are working against rural landowners by creating some "public engagement" fantasy that did not "engage" the landowners in the first place.  Hypocrite much?

About that MIT study... it's pure garbage.  The study makes  up a completely unsupported conclusion for why certain transmission line projects studied were abandoned:
  1. Public Participation: Local residents (their legislative representatives and public agencies) oppose projects in which they believe their worries are not adequately being attended to by the developer.

These projects were stopped because of opposition.  There is no education deficit that can quell opposition by "adequately attending to worries."  The only thing that stops opposition is to stop bad projects.  Landowners impacted by new electric transmission towers and lines across their working land and adjacent to their homes aren't deterred from opposition by being told that their worries are unfounded.  That just makes the landowners even more angry and determined to stop the project.

The only thing that can end opposition to a transmission project is not to engage the landowners in the first instance.  If you don't site overhead transmission across private property, then landowner opposition never forms.  Planning new projects buried on existing highway or rail rights of way, or underwater, is a guarantee that no landowners are affected in the first place.

Of course, a bunch of special interests that live in the big cities and think they should be provided with "clean energy" produced elsewhere have absolutely no idea what people that live and work in rural areas want.  If the cities want "clean energy" then they need to find ways to produce it themselves.  Build a new nuclear power plant in your own city.  It is not the responsibility of rural America to provide for all your needs.  Self-sufficiency is highly valued in rural areas.  You should try it sometime because rural folks will continue to resist.
2 Comments

FERC Engages in Political and Special Interest Narrative Building

12/17/2022

2 Comments

 
Picture
At the end of the week, the Federal Energy Regulatory Commission issued a Notice of Proposed Rulemaking entitled, "Applications for Permits to Site Interstate Electric Transmission Facilities."  Yes, it's just what it sounds like.  FERC is developing rules for applying for a federal permit from the agency.  This was made possible by last year's "Bipartisan Infrastructure Act" that gave FERC permission to issue a permit for interstate transmission in the event that a state denied one.  FERC's new rules are going to guide the process for a transmission developer to usurp state authority and use federal eminent domain to site a new transmission line on your property.

The NOPR itself contains a plethora of really awful ideas, and your job is to comment on them and advocate for something different.  Yes, it's a federal agency and you may find that daunting, but ultimately you are the one who is going to have to live within these rules so don't give up your only opportunity to say your piece.

One of FERC's absolutely ABSURD ideas is to allow a developer to engage in a pre-application process at FERC at the same time as it is engaged in a state application process for the project.  FERC reasons:
"The purpose of the pre-filing process is to facilitate maximum participation from all stakeholders to provide them with an opportunity to present their views and recommendations with respect to the environmental impacts of the facilities early in the planning stages of the proposed facilities."
FERC thinks you have nothing better to do than "participate" in its permitting process while you are also engaged in a state permitting process.  Double your time, double your effort, double your money!  And while we're doubling things here, it also costs the transmission developer double their costs to participate in two different permitting processes at the same time.  In many RTO-planned, cost allocated transmission projects, ratepayers (that's you) pick up the tab for all the permitting costs.  So this double permitting process costs you double!  The epitome of waste here is that if the transmission project is approved by the state (which it is in a vast number of instances) then the FERC permitting process becomes completely unnecessary!   Instead, FERC should sit back and wait until a state either approves or denies a project before giving transmission developers the green light to proceed with the FERC application.  It should wait until it knows whether the FERC process is even necessary before spending all that time and money on it.  FERC has not given a plausible reason for having to run these two permitting processes simultaneously.

Another FERC brain fart is titled "Eminent Domain Authority and Applicant Efforts to Engage with Landowners and Other Stakeholders."  This proposed rule governs how the applicant will "engage" with you.  FERC suggests:
...an applicant may demonstrate that it has met the statutory good faith efforts standard by complying with an Applicant Code of Conduct in its communications with affected landowners.
FERC purports that if a transmission developer files a "Code of Conduct" and promises to abide by it, then so it shall.  There is no enforcement, no investigation, no public forum to keep the developer honest.  FERC just takes the developer's word for it that you are treated well and that you will be all aboard for the transmission project if you are only "engaged with" early on.  We all know that transmission developer "codes" are not worth the paper they are written on.  They are nothing but a fig leaf.  There is no place to report a violation of the "code" and absolutely no enforcement of it.  This is utter garbage and serves no useful purpose.  If FERC needs to ensure that landowners are treated fairly, it needs to roll up its sleeves and get its hands dirty actually engaging with the public in an effort to keep the developer honest.

There's also some "environmental justice" box checking going on here.  An applicant must provide an Environmental Justice Public Engagement Plan.  This plan requires the developer to "meaningfully engage with potentially affected environmental justice communities."  What is an environmental justice community?
...the term “environmental justice community” includes disadvantaged communities that have been historically marginalized and overburdened by pollution. The term also includes, but may not be limited to, minority populations, low-income populations, or indigenous peoples.
These communities are rarely found along transmission routes in rural areas that all the interstate transmission projects traverse.  Despite the word "justice", it is not dispensed equally to all persons.  Are you an environmental justice community if you already have a transmission line or two (or a gas or oil pipeline, or a highway, or other visually polluting infrastructure) sited across your property?  We should definitely find out because they don't have a real definition here.

Perhaps the best part of this train wreck are the "concurrences" of Commissioners Danly and Christie that are attached at the end of the document.  Despite voting for this rulemaking, they both manage to find ways to criticize it.

Commissioner Danly wonders:
... whether the proposed rule constitutes good policy, such as, for example, whether it will be beneficial in determining whether to site electric transmission projects when the states have not done so, or whether the rule will tend to ensure almost nothing is ever sited.
But Commissioner Christie sums it up like this:
State regulators are much better prepared to deal with that myriad of local concerns, including concerns over routing and costs, than FERC. Furthermore, state processes are far more convenient and user-friendly than processes at FERC, if for no other reason than geographic proximity. So, waiting one full year to allow a state to “go first” and make its decision makes sense for a lot of reasons. One obvious reason is that if the line is truly needed, the state regulators will in all likelihood approve it, and no FERC staff time and resources will need to be expended at all. The whole mantra that goes “the states are blocking needed transmission all over the country!” is simply a political and special-interest narrative. The steadily mounting increases over the past decade in transmission rate base nationally, with concomitant skyrocketing increases in transmission costs to consumers, blows up the narrative that states are systemically blocking needed transmission lines. Contrary to the narrative, states need more authority to scrutinize transmission projects for need and prudence of cost, not less, to protect consumers.
Ignorant special interests writing legislation that they believe will help them fill their pockets is never smart.  It always results in dumb stuff like this.

If you want to be involved in a group effort to comment on this Rulemaking, let me know.

Happy Holidays!  Krampus had delivered a bulging bag of evil for good little landowners this year while they're distracted with family activities.  More to come...
2 Comments

GBE Won't Commit to its Project

12/11/2022

0 Comments

 
Picture
If you're a person in the Grain Belt Express target zone who is currently being harangued and pursued to sign an easement, or perhaps a utility regulator being told that GBE is a sure thing, you might find this interesting.

About a month ago, Invenergy filed with FERC a "Request of Grain Belt Express LLC for Prospective Tariff Waiver, Expedited Action, and Shortened Comment Period."

The gist of this filing is that MISO has tendered an interconnection agreement for GBE and Invenergy only has 60 days to negotiate and sign it, or to file it unsigned.  GBE's negotiation period ends December 31.  GBE wants FERC to grant a waiver so that Invenergy can wait until some time next year to sign the agreement and make two large deposits for the transmission upgrades its GBE project will cause.

GBE has applied at MISO for both interconnection of its project and injection rights.  Interconnection and injection rights are two separate things.  Interconnection allows GBE to connect to MISO's existing system, but injection rights allows GBE to inject a certain amount of electricity into MISO at the interconnection site.  Both the interconnection and injection rights require MISO study to identify and plan any upgrades to the system that they will cause.  Interconnection and injection rights run on two different study tracks.  MISO determined that GBE's interconnection will require approximately $144,248,000 worth of work to the existing system to support the interconnection.  However, MISO has not yet completed the study that will determine the cost of the injection rights work, although GBE estimates it will be an additional more than $177 million.  GBE wants to know the injection rights number before it negotiates and signs the interconnection agreement, because once it signs the agreement it is obligated to make non-refundable deposits totaling approximately $77 million before it knows the injection rights number.

Let that sink in... Invenergy doesn't want to spend money on a project without knowing its full cost.  As Invenergy puts it
Otherwise, GBX will be placed in the position of having to decide whether to commit millions of dollars in security or cash pursuant to the executed TCA before it understands its total upgrade cost exposure associated with the Injection Rights.
This would have absolutely no relevance if there was not the possibility that Invenergy would cancel this project if the injection rights end up costing too much.  If Invenergy is going to proceed with GBE no matter how much injection rights cost, then the deposits don't matter.  The deposits would only represent a loss for Invenergy if it cancelled the project.

Apparently Invenergy is not going to know whether its project is going to proceed until at least the end of April, 2023.  But yet there are reports that Invenergy is filing eminent domain suits and taking landowners to court.  And, of course, Invenergy is pushing state regulators to approve its project in a big ol' hurry, even though Invenergy wants another 5 months to decide if its even going to proceed with interconnection to the existing transmission system (and that's if MISO's study gets completed on time, which in these days of clogged interconnection queues may not happen). 

Invenergy says having to put up cash as surety for its project is "too risky" for the company but taking your land via eminent domain isn't risky at all for Invenergy.  It's all about who bears the real risk, isn't it?
0 Comments

More Transmission Dead Ends

11/11/2022

3 Comments

 
Our bloated government and its clean energy sycophants are on a high-speed transmission train to nowhere and a crucial bridge is on fire.  Trouble ahead!  Can these self-important bloviators cross the bridge to Unicorn Utopia before it completely burns through?
Of course not.  This bridge has been burning for several years now and is pretty thin.  I'm talking about the landowner bridge... the landowners who are expected to accept the greatest impacts of new transmission lines on new rights of way across their private property. 

The Unicorn Engineers are positively obsessed with finding the solution to transmission opposition.  They continue to dream up stupid, unworkable ideas that will only further delay Unicorn Utopia.  How do I know this?  Because I have been a transmission opponent, and more importantly I have listened to the stories of hundreds of transmission opposing landowners over the past 15 years or so.  Why are the Unicorn Engineer ideas so bad?  Because they have never been transmission opponents and they have little understanding of how and why opposition forms and acts, and have never felt the emotions that go into landowner battles.

This week I came across a couple of bad ideas and one bright spot.

The first is an op-ed in Utility Dive written by former state and FERC Commissioner Tony Clark.  He talks about dumb plans to federalize transmission permitting.
The renewables spurred by the IRA require a considerable transmission buildout. Accomplishing it will be no mean feat. The most oft-proposed solution is to federalize ever more of the transmission planning and permitting process. That may sound better in theory than in practice.

Furthermore, the federal government has a dismal record in streamlining infrastructure permitting, even when it is needed. Look no further than the Western U.S., where federal lands are often an obstacle to transmission, rather than a facilitator of it.

So... permitting reform... Big NO!

But then Clark combine electrics transmission permitting with gas pipeline permitting to incorrectly conclude that we need to cripple NEPA.
Infrastructure opponents have had increasing success obstructing projects with a federal nexus. FERC’s natural gas pipeline certification program is a good reference point. Activists have blocked needed energy projects through the aggressive use of litigation at every step of the permitting and review process. Without meaningful reform to federal laws like the National Environmental Policy Act and the Clean Water Act, all those litigation weapons will now be in the hands of interveners seeking to stop electric transmission lines.
Can you say hypocrites, Tony?  The ones who use NEPA as a battering ram would never stoop to help an electric transmission opponent.  Despite pretending that their opposition is about landowners and the environment, the truth is that the big green groups are motivated by politics, grants and donations that pay fat salaries.  Landowners and the environment be damned.  The fact is that electric transmission opposition is devoid of politics.  We're about what unites us as landowners, not what divides us at the ballot box.  We've already got a great strategy and a bottomless bag of tricks developed over the years.  We don't need to be hypocrites like the environmental groups.

And here's a different article with another stupid idea -- bribing unaffected community members to accept impacts ON THE LAND OF THEIR NEIGHBORS.
Beyond just educating the neighbors of a proposed project, former U.S. Rep. Joseph P. Kennedy III (D-Mass.), now managing director of Citizens Energy, said developers and utilities should explore ways to ensure that the expansions directly benefit those communities.

Such arrangements can prove worthwhile even to for-profit companies by alleviating residents’ concerns that large transmission projects could lower property values or disrupt their neighborhoods with no visible benefit to them, Kennedy said. The costs of the delays or resiting of projects can often well exceed the expense of profit sharing with those communities, he argued.

But this doesn't work either.  Landowners with new transmission on their property are the ones leading the opposition and they are not going to be deterred by bribes paid to their neighbors.  Those bribes don't do a thing to alleviate the landowner burden.  The bribes actually juice opposition to work harder.

And here's another stupid idea from the same article:
Former FERC Commissioner Colette Honorable, now a partner at Reed Smith leading the firm’s energy regulatory group, noted that getting all parties on board with a project in the early phases can reduce the likelihood of prolonged, and expensive, delays at FERC and the federal courts.
Earlier engagement does not bear fruit unless there is compromise on both sides.  What do impacted landowners get from earlier engagement?  If it's not something that prevents impacts, such as burial along existing rights of way like highways, or reconductoring existing lines, then landowners get nothing.  Again, urging people to throw your neighbor under the bus is not a successful strategy.

But Honorable does offer some valuable insight gleaned from her years as a state and federal regulator.
“You’re in trouble if you have a matter pending and the first time you hear them is when they object,” she said.

Likewise, she said incorporating equity into the work done by RTOs can be accomplished by examining what voices are missing at the table and including those stakeholders who aren’t represented.

It's so simple, it's stunning.  Landowners are the missing voices.  Ignoring them absolutely guarantees that the opposition will continue.
Picture
3 Comments

Misinformation Won't Help Grain Belt Express

11/5/2022

0 Comments

 
Picture
The Silly Old Man's Club of Kirkwood must have had a Halloween meeting where this blog was dreamed up: "Tiger Connector" Planned:  Kirkwood Electric Gets A Bit Of Good News On Energy Front. 
It did scare the bejeezus out of me, but only because it is so completely misinformed and contains a number of outright falsehoods.  I will have to say that this blog is appropriately named:  Environmental Echo.  Just an echo chamber for all the crazy enviro-whacko claims being made that don't have any basis in truth. 

Let's start with this lie: 
“We’re well on our way because the project has obtained an overwhelming majority of the easements, now has Public Service Commission approval, and now has a legislative framework,” said Petty.
The "Tiger Connector" does NOT have PSC approval.  In fact, without approval of the specific "Tiger Connector" addition, the "approved" Grain Belt Express project does not have any place to connect to the Missouri electric grid.  When the project was initially approved in 2019, it was planned to make a 500 MW connection in Ralls County.  At some point new project owner Invenergy decided that interconnection was not viable and applied with regional grid operators to move its interconnection point to Callaway County and increase its size five-fold.  This interconnection of 2500 MW is still not fully approved by the regional grid operator.  Who knows where or when (or IF) GBE will ever connect.  In addition, the Missouri PSC is now evaluating the project anew and may not approve the changes.

As far as the easements go, let's clear that up, shall we?  Many easements have been obtained through coercion and threats of condemnation using eminent domain authority.  It's not like all landowners who have signed easements under duress "do understand it and are on board."  In addition, Invenergy is pursuing easement acquisition through the courts for a growing number of properties.  These landowners didn't knuckle under and sign an easement out of fear but are determined to fight Invenergy tooth and nail all the way to the end.

Lastly, what is this "legislative framework"?  Just because some agricultural organizations took it upon themselves to negotiate meaningless "protections" for landowners in a sneaky fashion that did not include the landowners themselves does not mean that landowners are "on board" with the way they were stabbed in the back during the last legislative session.  All that aside, the SOMC of Kirkwood should be aware that Invenergy made sure to file its application for the "Tiger Connector" just days before this new "legislative framework" took effect.  It will not apply to Grain Belt Express therefore, even if it was useful, it will not come into play.

And what kind of a "reporter" takes this kind of statement at face value and does not bother to verify it?
“Invenergy has always been more than generous to the farmers with their compensation for access to their property. Its supported the generous compensation spelled out in a legislative compromise that was reached in 2021,” said Petty of Kirkwood Electric.

“While a few farmers still remain skeptical about Invenergy’s intention to make this a win-win situation for all, over 70% of the landowners and a majority of folks do understand it and are on board,” Petty added.

Spoken like a true NIMBY who won't find Grain Belt Express in his own back yard.  Petty has NO contact with "farmers" and does not speak for them.  He has NO IDEA what they want and what they think.  Pretty brassy to tell those farmers how great GBE will be for them, don't you think?  Maybe you should contact him and let him know the truth so he can stop spreading misinformation.

Speaking of misinformation, what could this mean?
... Grain Belt Express, which has scored some recent successes.
Recent successes?  Where?  How?  WHAT?  There have been no "recent successes."  It's just a platitude that means nothing.

And then there's this:
...Chicago-based Invenergy, which has now navigated objections to the line from rural legislators and groups like the Missouri Farm Bureau.

State legislators with ties to the fossil fuel industry have opposed the wind energy project. Farm groups also have fought the project for years over opposition to the use of eminent domain for siting of transmission towers.

Some rural landowners and farmers supported legislation meant to derail the project, including one proposal that would have given county commissions veto power over transmission projects. Farmers wanted more money for land acquisition, and resulting legislation could have killed the project.

So much misinformation in this short blurb it's hard to know where to begin.  First of all, the opposition to this project has always come from affected landowners who object, not to clean energy, but to the use of eminent domain to take new easements across their working farmland.  It places an impediment on the productivity of the entire parcel and costs farmers additional money and time and results in lower yields.  Farm Bureau and other agricultural groups took it upon themselves to defend their members through lobbying at the legislature.  But the Ag groups got a little too carried away last year and forgot about the landowners they were supposed to be working for.  This doesn't mean landowners are "on board" with any of last year's meaningless legislation.  Invenergy is probably still snickering at how easily the Ag groups fell for their bait and switch.  And now the Ag groups are ticked off because they've been made to look foolish.

Legislators have been responsive to their constituents' opposition to Grain Belt Express.  Their legislative agenda is driven by their constituents, not by any "ties to the fossil fuel industry."  That's a disgustingly common Sierra Club talking point that is no longer true.  People don't like ANY energy infrastructure in their community, and certainly not on their land, especially when they derive no benefit from it.  Quit whining about the "fossil fuel" devils.  The only devils buying legislators these days are "clean energy" companies.  Clean or dirty, it's all about corporate profit.  Don't lose sight of that.

Where's the proof that "farmers wanted more money for land acquisition"?  This statement is concocted out of speculation and ignorance.  Farmers actually say that their land is not for sale at any price!  And can we talk some truth about price here for a hot minute?  Eminent domain for utilities insures that the utility can acquire the land it needs to serve customers at "fair market value" instead of actual market value.  The money the utility saves on land acquisition flows back to their customers in the form of lower rates.  This is what's known as "cost of service" rates.  The customers are charged what it costs the utility to serve them, plus reasonable return.  In the case of Grain Belt Express, however, their project does not use "cost of service" rates.  Instead it's what's known as a "merchant" transmission project that negotiates with voluntary customers to agree on a market based rate for service.  The price GBE can charge depends on how much the voluntary customers will pay in a free and fair market.  It is completely divorced from GBE's "cost of service."  In GBE's case, the difference between it's cost of service and the market based rates it negotiates represents the company's profit.  The cheaper the project is to build, the bigger Invenergy's profit.  The market sets its rates, not its cost of serving customers.

Then there's this misinformation:
According to Petty, Missouri cities like Hannibal, Springfield and Kirkwood have supported the energy project for years. He said everyone is “jumping on the bandwagon now” and the cleaner, cheaper energy for Missouri will save money for homeowners and businesses.
Who's jumping on the bandwagon?  Nobody, that's who.  Invenergy has not revealed any new customers for its project since the Missouri cities got a below-cost deal handed to them back in 2016 in order to score PSC approval.   GBE has had authority to negotiate voluntary customer "negotiated rate" contracts since 2014.  In all the time since, Invenergy has only managed to announce one customer for less than 10% of its proposed Missouri capacity.  Only the Missouri municipalities thought GBE was a good deal.  Other potential customers have avoided it like the plague.  Does the cities' contract represent a fantastic opportunity that everyone else is missing out on?  It's more likely that the cities signed on to something that everyone else doesn't want.  It's not like the Missouri cities are really smart about buying power.  They bought a healthy share of the Prairie State coal-fired generation complex AFTER Missouri voted for clean energy in 2008.  Doesn't sound very smart to me.

And here's your completely clueless ending:
“While a few farmers still remain skeptical about Invenergy’s intention to make this a win-win situation for all, over 70% of the landowners and a majority of folks do understand it and are on board,” Petty added.

According to Petty, it’s just a matter a time before everyone will be on the same page with the Grain Belt project.
By that token, has Petty considered that 90% of Grain Belt's potential Missouri Customers, and 100% of its potential PJM customers, are NOT on board with it?  If 70% of needed easements equals landowner support, then 95% of customer avoidance equals utility opposition. 

It's just a matter of time until Grain Belt Express collapses in a heap and the SOMC of Kirkwood gets left with drool on its collective chin.
0 Comments

Same Old Tired Ideas Can't Solve Transmission Issues

10/30/2022

2 Comments

 
A webinar was held on Friday that attempted to solve   "the big question is whether there is enough political will to overcome the forces of NIMBYism (Not In My Backyard) to secure new rights-of-way through states and localities that aren’t direct beneficiaries."  Or at least discuss this issue.  Although the host did a remarkable job of trying to keep the event on topic, and to include questions from the audience as well as those from invited media, the panelists wrecked the event by side-stepping questions and talking about things that completely avoided the topic of the webinar.  There were absolutely no new thoughts, ideas, or plans to solve the NIMBY issue.

The panelists were Maria Robinson from DOE's new "Grid Deployment Office", a guy from EEI, a guy from a transmission company, and our old pal Michael Skelly.

Maria Robinson might have been the biggest disappointment.  She shared that industry and government need to work together to get transmission built.  Where are the so-called NIMBYs in this equation?  She doesn't want to acknowledge that affected people even exist.  How is it that landowners are supposed to gladly surrender their property for new transmission when they don't get any respect?

I asked her the following question:  In a recent interview you said, “We’re really looking at engaging the folks that will be most impacted potentially”, while also mentioning “a pot of money that could be used for economic development in communities impacted by interstate transmission lines.” Since landowners who will have to look at and work around new transmission lines every day are “most impacted” how would economic development in the broader community compensate the most affected landowners? Wouldn’t the money be better spent lessening impact on most affected landowners?

Maria's answer side-stepped the question, which was how does she square her concern for "most affected" with doling out financial bribes for "impacted communities"?  Instead of comparing/contrasting directly impacted landowners with local community organizations or governments that are not directly affected (but are financially rewarded for the misery or others), she simply pointed the finger at Congress and said the legislation they passed did not allow her to award money to landowners.  She refused to recognize that paying bribes to entities that are not affected does absolutely NOTHING to solve the NIMBY problem.

Robinson might actually believe that transmission is built to satisfy "needs" of consumers.  Consumers already have electricity -- the great renewable push is being undertaken to satisfy the "needs" of political ideology.  Just a bunch of government functionaries, spending money Congress is taking out of YOUR pocket and accomplishing absolutely nothing at all.

She thinks her job is to  "bring stakeholders together" and "help them understand why transmission is important."  But she only mentioned engaging states and tribes in particular, not landowners.  She even had the gall to claim that "we" have found that engaging stakeholders earlier and more often "helps" alleviate the local concerns around transmission that leads to significant delays.  Who is "we", Maria?  There is absolutely NO EVIDENCE that these affected NIMBYs can be re-educated to accept impacts and make personal sacrifices for politically-motivated electric transmission projects.  In fact, the evidence (piles of actual studies on transmission opposition) shows the exact opposite.  Landowners don't respond to propaganda and glad-handing.  And landowners are the ones who carry out the long and loud opposition that delays (or cancels) transmission projects.

The first thing Maria needs to do, if she actually wants to succeed instead of just wasting taxpayer funds treading water in a political quagmire of transmission delays, is recognize those NIMBYs and find out what it is they really want.  Until that happens, she's just another big government disappointment.

One of the reporters asked when transmission became a political issue and was laughed at and told it's always been political.  The real answer is that transmission became a political issue when the transmission itself was proposed for political reasons.  We've built a lot of transmission in this country in the past in order to provide plentiful electricity to all who wanted it.  It's when additional transmission started to be proposed to favor the generation resource fad of the decade (whether it was coal and gas, or today's wind and solar) that opposition began to develop.  And opposition is winning.  I have a huge list of electric transmission projects that have been proposed in the past but ultimately abandoned, or significantly modified, because of delays caused by entrenched opposition.  The opposition now has the upper hand and Maria has absolutely NO WORKABLE PLAN to deal with it.

She seemed to recognize that reconductoring existing transmission to increase its capacity can be done "faster" and without the opposition headaches, but she didn't seem to understand why.  It's because reconductoring doesn't take new rights of way across previously unaffected property.  It's the new rights of way that are the problem.

Someone named Elizabeth Weiss submitted a question that began by recognizing that Wisconsin has had success in building out its transmission network by utilizing existing highway rights of way instead of taking new land and asked if siting transmission on highway rights of way might be a national model that could be employed to get things accomplished.  Bravo, Elizabeth, whoever you are!  You hit the nail on the head!  Unfortunately the panelist who sidestepped this question blathered on about a "national will to build transmission" and that we need the government to make new transmission corridors.  What?  Hello?  It's the new rights of way that are the problem!  Not "national will".  There's no way to impose any "national will" on landowners who know that they don't NEED to sacrifice new rights of way when existing rights of way are right there for the taking. 

Landowners and their forthright opposition groups have been asking for the "national will" to have a conversation about using existing rights of way in order to avoid new impacts, however they have been consistently ignored.  We're not going away.  We're only going to get louder and larger until we become part of the solution, instead of just a problem to be side-stepped or silenced with greater government power.

Maria ended the webinar with a big smile and assured everyone, "It's a great time to get involved" in transmission.  Unless you're a landowner, Maria, then it's a terrible time to have politically motivated transmission sited across your land, next to your home and in the middle of your farm food factory.  How completely tone deaf, Maria Robinson!

And, of course, the event wouldn't have been complete without Michael Skelly trying to answer every question posed (even when it was directed at someone else).  His "uhhh" punctuated sentences, incorrect facts (it's really Southern Cross, not "Southern Spirit") and useless interjections are worse than ever.
Picture
I know we've all gotten older since the Clean Line days, however, some of us have aged faster than others.  Maybe it's time to retire and go play on the fire pole?

I was greatly entertained by this webinar, however I'm not sure how useful it was for solving the transmission problem.  As one audience member opined, "If I was one of the reporters, I would have come away wondering what there was to write about."  Indeed!  Just the same old panelists with the same old, tired ideas.
2 Comments

That Time Invenergy Bought a Permit, Not a Project

10/29/2022

0 Comments

 
The Missouri Landowners Alliance filed a brilliant Motion at the MO PSC yesterday.  The Motion caused a thought and understanding explosion on my part.  How did everyone miss this until now?

The premise of the motion is that Grain Belt Express had abandoned its permit (CCN) when it made major modifications to the Grain Belt Express project.  Therefore, if the CCN for Grain Belt Express that was issued years ago is no longer valid, then GBE would have to file a new application for its new project and hope it received a new CCN.

Think about this...
Picture
Miss Kitty Hamm doesn't fit inside the box she's tried to jam herself into.  The box is sized for a different, much smaller cat.  No matter how hard she tries, she simply can't squeeze her bulk in to a box that doesn't fit.  The same can be said about Invenergy's Grain Belt Express project.

Once Invenergy bought the Grain Belt Express transmission project from now defunct Clean Line Energy Partners in 2019, it began to systematically abandon and reshape the project until it's now become a whole new project.

Changed facts:
  1. Name change from Grain Belt Express Clean Line to just plain old Grain Belt Express.
  2. Went from 206 miles of direct current line across Missouri to somewhere in the neighborhood of 254 miles of mixed DC/AC lines.
  3. Changed its route to add a 40-mile AC "Tiger Connector" and take new rights of way from previously unaffected landowners.
  4. Location of converter station went from Ralls Co. to Monroe Co.
  5. The Ralls Co. converter was located "nearby" the proposed interconnection point.  The new Callaway Co. interconnection point is 40 miles from the new converter station in Monroe Co.
  6. Desired interconnection point went from Ralls Co. to Callaway Co.
  7. Added a new A/C substation in Callaway Co.
  8. The capacity of the line went from 4,000 to 5,000 MW.
  9. The capacity offered for sale in Missouri went from 500 MW to 2,500 MW.
  10. Since converter station size was drastically increased it may cause a corresponding price increase of $500M.
  11. Tower structures went from monopoles to 4-legged lattice masts.
  12. Landowner payments went from 110% FMV plus structure payments, to 150% FMW without structure payments.
  13. Grain Belt has morphed from one continuous project between SW Kansas and Indiana into some "two phase" hybrid, of which certain portions may or may not be built.  In fact, it seems that GBE has split into two distinct projects:  A)  SW Kansas to Callaway Co. Missouri; and B)  Callaway Co. Missouri to Indiana.  These two "phases" will operate independently through the permitting and construction phase.
  14. Cost of the project went from $2.9B to $5.7B, nearly double the cost.
  15. Grain Belt Express says that it is now selling "undivided interest (purchase or lease) or long-term contracts" instead of the negotiated rate contracts for capacity approved by the Federal Energy Regulatory Commission for Grain Belt Express Clean Line.  It's currently unclear whether the new Grain Belt Express even has an approved rate for its new project.  Without a rate or sale to "the public" is GBE even a "public utility"?
These are major changes.  Major changes so substantial that they are, in effect a new project.  However, Invenergy is trying to stuff them into the custom permit box the PSC built for Clean Line's Grain Belt Express project.  These two new projects just don't fit in the permit box. 

Grain Belt Express has changed so drastically that is no longer resembles the project that the MO PSC permitted.  Was Invenergy ever interested in building the Grain Belt Express project that the PSC has permitted and that it swore it was going to build when the PSC approved its purchase of the project?  Or was Invenergy only interested in buying a permit for a transmission project (a box) into which it could stuff a completely different transmission project without having to get permitted for the project it actually intends to build?  I seem to remember some requirement Invenergy tacked onto its purchase of the project that made the purchase contingent upon the state commissions approving the new ownership of the permit.  I'm starting to think that Invenergy only bought a permit, not a project.

When the PSC permitted Grain Belt Express Clean Line, it added a condition that says:
“If the design and engineering of the project is materially different from how the Project is presented in Grain Belt Express Clean Line LLC’s Application, Grain Belt Express Clean Line LLC must file an updated application with the Commission for further Commission Review and determination.”
A new application for a new project.   A new application requires a new review.  There's absolutely nothing in that condition that guarantees the existing approval will remain in place for a new application for a different project from a different owner.  Are MO PSC permits transferable commodities now that can be sold from company to company and be molded to guarantee approval of a completely different project?

Let the PSC know how you feel about this slight of hand (case number EA-2023-0017).  A materially different project requires a completely new review by the PSC.
0 Comments

Look out below!  New plan to build transmission across the Midwest

10/17/2022

3 Comments

 
The U.S. Department of Energy held another one of its wonderfully transparent webinars where it revealed its game plan for concocting a National Transmission Plan Study as required by Green New Deal laws passed last year.  Such information was presented to "the public" and only a select few were allowed to question or comment on it.  Regular folks were not among the anointed.
Picture
The chat, where attendees were urged to ask questions, was disabled.  That's how we pretend "transparency" without actually providing it.  But you are allowed to submit your comments via the DOE's website (see link at the bottom of the page) although it's a bit like screaming down a well.  Your comments are never acknowledged or affirmed.

DOE says its plan is supposed to "complement" existing regional transmission planning under FERC's bailiwick, and not take its place.  However, DOE says its goal is to "get steel in the ground" by identifying and funding new projects using all that taxpayer cash the new law allows them to dole out. Identifying and financing new transmission DOES interfere with regional planning because those are the projects that greedy developers will flock to, not the regionally planned projects that are actually needed to keep the lights on.  So much prevaricating....

DOE says that building new industrial scale wind and solar are the only "needs" it is considering for a new suite of massive transmission projects.  By doing this, DOE is putting its thumb on the scale and selecting certain kinds of generation over other possibilities, such as distributed generation, gas, hydrogen, carbon capture or nuclear.  DOE is not considering any other forms of generation except utility-owned solar and wind.  DOE even admitted that without its plan and subsidies that more distributed generation would get built, so therefore DOE is trying to cripple distributed generation in your local area.

When asked how this plan fits with the plan to build offshore wind, which needs a different kind of transmission, DOE dismissed that, saying that a different DOE planning exercise is in the works for that and they are not considering it.  DOE is at war with itself, pushing two different plans for two very different generation possibilities.  While the National Transmission Planning Study is looking at massive new lines stretching eastward from the Midwest, the Offshore Wind Transmission study is looking at shorter lines from the offshore wind generators to the eastern cities who will use the power.  Which one will win?  We don't need both.  DOE doesn't care which one is ultimately selected, it's just busy spending taxpayer money conducting two very different studies that are in conflict with each other.  This is the epitome of waste!

The DOE "scientist" even said its plan was "a bit of an artificial thing because of how the program works."  The program is all about reaching artificial goals and doesn't let any nasty reality intrude. It doesn't consider anything other than a bunch of new industrial solar and wind generators in the Midwest, and it makes no accommodations for siting impediments that could insert a little reality into their "plan."  Only the DOE's artificial fairy tale of what future generation looks like is considered.  This fairy tale isn't going to have a happy ending.

Here's some maps of what the "program" spit out as likely new transmission corridors.  Notice how all the lines go from the Midwest to the east?  That was confirmed as the DOE's National Transmission Plan.  Generate power in Midwestern states and ship it over new transmission lines to eastern cities.
Picture
Don't like this garbage?  Write to your elected representatives and let them know!  DOE's National Transmission Planning Study is a wasteful fairy tale that is never going to happen.  But, hey, what do these little government functionaries care?  They're drawing a paycheck and they don't live anywhere near any of these new lines.
3 Comments
<<Previous
Forward>>

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.